To make informed decisions in futures markets of electric energy, stochastic programming models are commonly used. Such models treat stochastic processes via a set of scenarios, which are plausible realizations throughout the decision-making horizon of the stochastic processes. The number of scenarios needed to accurately represent the uncertainty involved is generally large, which may render the associated stochastic programming problem intractable. Hence, scenario reduction techniques are needed to trim down the number of scenarios while keeping most of the stochastic information embedded in such scenarios. This paper proposes a novel scenario reduction procedure that advantageously compares with existing ones for electricity-market problems tackled via two-stage stochastic programming.
To reduce the computational burden of capacity expansion models, power system operations are commonly accounted for in these models using representative time periods of the planning horizon such as hours, days or weeks. However, the validity of these time-period aggregation approaches to determine the capacity expansion plan of future power systems is arguable, as they fail to capture properly the mid-terms dynamics of renewable power generation and to model accurately the operation of electricity storage. In this paper we propose a new time-period clustering method that overcomes the aforementioned drawbacks by maintaining the chronology of the input time series throughout the whole planning horizon. Thus, the proposed method can correctly assess the economic value of combining renewable power generation with interday storage devices. Numerical results from a test case based on the European electricity network show that our method provides more efficient capacity expansion plans than existing methods while requiring similar computational needs.
11 January 2019 in IEEE Transactions on Power Systems
The transmission-constrained unit commitment (TC-UC) problem is one of the most relevant problems solved by independent system operators for the daily operation of power systems. Given its computational complexity, this problem is usually not solved to global optimality for real-size power systems. In this paper, we propose a data-driven method that leverages historical information to screen out network constraints in the TC-UC problem. First, past data on demand and renewable generation throughout the network are used to learn the congestion status of transmission lines. Then, we infer the lines that will not become congested for upcoming operating conditions based on such learning and disregard their capacity constraints. This way, we formulate a reduced TC-UC problem that is easier to solve. Numerical results on a medium- and a large-size power system show that the proposed approach outperforms existing ones by significantly reducing the computational time while obtaining solutions that are equal or close to the one obtained with the original TC-UC problem. Furthermore, the purely data-driven method we propose can be seamlessly complemented with a constraint generation procedure to guarantee that the optimal solution to the original TC-UC problem is eventually recovered.
1 December 2013 in IEEE Transactions on Smart Grid
Industrialized countries are increasingly committed to move towards a low carbon generating mix by increasing the penetration of renewable generation. Additionally, the development in communication technologies will allow small end-consumers and small-scale distributed energy resources (DER) to participate in electricity markets. Current electricity markets need to be tailored to incorporate these changes regarding how electricity will be generated and consumed in the future. The EcoGrid EU is a large-scale EU-funded project, which establishes the first prototype of the future European intelligent grids. In this project, small-scale DERs and small end-consumers can actively participate in a new real-time electricity market by responding to 5-min real time electricity prices. In this way, the market operator will also obtain additional balancing power to cancel out the production variation introduced by renewable electricity generation. The real-time market concept architecture for EcoGrid EU is introduced in this paper, which provides a market-based platform and information and communication technology (ICT) infrastructure that extends the current electricity market to a shorter time horizon and to smaller assets.