In modular construction projects, unit production and onsite work are conducted concurrently, enabling shorter duration, lower cost, and improved quality. Because of the nature of the work, building design details should be determined early in the design phase, which requires information from participants. However, the design process for stick-built construction does not include such information, which leads to errors in design, such as omissions and conflicts of information from participants, causing reworking in the design phase. To reduce errors, an information flow should be identified representing when/what/how the information should be shared, and with whom. This paper proposes an integrated design process based on the information flow. To identify the flow, a precedence relationship between activities is represented using a dependency structure matrix (DSM). Then, the order of activities is rearranged using a partitioning algorithm. In this manner, unnecessary feedback and reverse information flow, which are related to errors, are reduced. Finally, the rearranged activities are proposed as an integrated design process. To validate the impact of the proposed process and methodology, interviews with experts were conducted. The validation results suggest that the project delivery method should also be considered in the early project phase in practical application.
4 May 2021 in Journal of Asian Architecture and Building Engineering
Modular construction offers benefits such as high quality, low cost, and short durations owing to the high productivity of repetitive production. To maximize productivity, modular construction involves repetitive schedules; however, the scheduling methods exhibit limitations when applied to on-site work. These methods are optimized by adjusting the production rate of activities; however, the bounds of the production rates of modular construction on-site work are limited because of workspace limitations in the units and varying amounts of work between activities. This results in idling time in the scheduling methods. Thus, in this research, the parallel station method (PSM) was employed to ensure a flexible production rate. A discrete event simulation model was developed and employed to estimate the number of workers and work duration. The results demonstrated the following: 1) The developed scheduling method exhibits better results than the method for stick-built construction. 2) When applying the PSM, the line-of-balance method is cost-effective, while the TACT method is time-effective, implying that scheduling methods should be selected based on the primary objectives of modular projects. The findings of this research will contribute toward improving the accuracy and applicability of repetitive scheduling methods and reduce the labor cost and duration of on-site work.