The automated load-haul-dump (LHD) machines have the potential to increase productivity and improve safety, but there are many issues to be considered when optimising the operation of LHDs. Today's focus on improved equipment reliability is part of the problem, and another difficult issue is the special conditions and constraints of the operating environment. For automated LHDs, the latter issue is even more important, as humans have been removed from the production area and are not close by to solve the problems. The purpose of this paper is to find the causes of LHD idle time and to study their impact on the operation of LHDs. In this study, real-time process data and maintenance data from an underground mine in Sweden have been refined and integrated. The study takes into account the complexity of the mine environment, discusses the factors to be considered when optimising and automating the operation and uses fault tree analysis (FTA) to analyse the idle time.
28 November 2013 in Quality and Reliability Engineering International
As the near surface deposits are being mined out, underground mines will increasingly operate at greater depths. This will increase the challenges related to transporting materials from deeper levels to the surface. For many years, the ore and waste transportation from most deep underground mines has depended on some or all of the following: truck haulage, conveyor belts, shafts, rails, and ore pass systems. In sub-level caving, and where ore passes are used, trains operating on the main lower level transport the ore from ore passes to a crusher, for subsequent hoisting to the surface through the shaft system. In many mines, the use of the ore pass system has led to several problems related to the ore pass availability, causing production disturbances and incurred cost and time for ore pass rehabilitation. These production disturbances have an impact on the mining activities since they increase the operational costs, and lower the mine throughput. A continued dependency on rock mass transportation using ore passes will generate high capital costs for various supporting structures such as rail tracks, shaft extensions, and crushers for every new main level. This study was conducted at an existing underground mine and analyzed the transport of ore from loading areas at the lower levels up to the existing shaft points using trucks without employing ore passes. The results show that, when the costs of extending ore passes to lower levels become too great or ore passes cannot be used for production, haul trucks can be a feasible alternative method for transport of ore and waste up the ramp to the existing crusher located at the previous main level. The use of trucks will avoid installing infrastructure at the next main level and extending the ore passes to lower levels, hence reducing costs.
11 August 2014 in International Journal of Mining, Reclamation and Environment
This paper compares three ways to operate a load haul dump (LHD) machine, manual operation, automatic operation (fleet operation) and semi-automatic operation, to find the best operating mode. In a fault tree analysis, different failures are classified and analysed, but the way to recover from certain states is not accounted for, which is something a Markov model can handle. The paper is based on the analysis of real data from an underground mine. A Markov model has been built for mining application and it is shown that a semi-automatic LHD has the highest probability of being in a productive state since it has the advantage of changing operating modes (manual and automatic) depending on the need and situation. Hence, the semi-automatic LHD is the best choice from an operational point of view. The paper fills a gap in the literature on manual vs. automatically operated LHDs by providing a new way of evaluating the operating mode of LHDs using Markov modelling, while considering the operating environment.
A detailed understanding of the drilling system and the drilling control is required to correctly interpret rock mass conditions based on monitored drilling data. This paper analyses data from hydraulic in-the-hole (ITH) drills used in LKAB’s Malmberget mine in Sweden. Drill parameters, including penetration rate, percussive pressure, feed pressure, and rotation pressure, are monitored in underground production holes. Calculated parameters, penetration rate variability, rotation pressure variability, and fracturing are included in the analysis to improve the opportunity to predict rock mass conditions. Principal component analysis (PCA) is used to address non-linearity and variable interactions. The results show that the data contain pronounced hole length-dependent trends, both linear and step-wise linear, for most parameters. It is also suggested that monitoring can be an efficient way to optimize target values for drill parameters, as demonstrated for feed force. Finally, principal component analysis can be used to transfer a number of drill parameters into single components with a more straightforward geomechanical meaning.