At complex industrial sites, the high number of large consumers that make the technological process chain requires direct supply from the main high-voltage grid. Often, for operational flexibility and redundancy, the main external supply is complemented with small local generation units. When a contingency occurs in the grid and the main supply is cut off, the local generators are used to keep in operation the critical consumers until the safe shutdown of the entire process can be achieved. In these scenarios, in order to keep the balance between local generation and consumption, the classic approach is to use under-frequency load-shedding schemes. This paper proposes a new load-shedding algorithm that uses particle swarm optimization and forecasted load data to provide a low-cost alternative to under-frequency methods. The algorithm is built using the requirements and input data provided by a real industrial site from Romania. The results show that local generation and critical consumption can be kept in stable operation for the time interval required for the safe shutdown of the running processes.
In many countries, most one-phase residential electricity consumers are supplied from three-phase, four-wire local networks operated in radial tree-like configurations. Uneven consumer placement on the wires of the three-phase circuit leads to unbalanced phase loads that break the voltage symmetry and increase the energy losses. One way to mitigate these problems is to balance the phase loads on the feeders by choosing the optimal phase of connection of the consumers. The authors proposed earlier a phase balancing algorithm based on metaheuristic optimization. For networks with a high number of supply nodes, this algorithm requires finding a solution for all the consumers simultaneously. Two alternative approaches are proposed in this paper that use the tree-like structure of the network to divide the optimization between a main distribution feeder and several branches, creating a multistage process, with the aim of minimizing energy losses. A case study is performed using a real low-voltage distribution network and a comparison is made between the three algorithms. The resulting losses have marginal variations between the proposed approaches, with a maximum of 1.3% difference.
1 December 2021 in Bulletin of the Polytechnic Institute of Iași. Electrical Engineering, Power Engineering, Electronics Section
The successful operation of back-up supply sources in the case of dynamic loads transfer in industrial electricity supply installation is mainly depending on the mitigation of the residual voltage that appears in fault scenarios that result in losing supply from the main grid. The decrease of the interval of presence of residual bus voltage depends highly on the local load and the network configuration. A high time constant (seconds) of the decreasing residual voltage can lead to the disconnection of critical consumers. In this paper, it is presented a simple, cost-effective method for dynamic load transfer that can replace the Motor Bus Transfer approach. The validity of the method is tested on a real large industrial site from Romania. The case study shows that the proposed approach can achieve a voltage return time of around 750 ms.
1 December 2022 in Bulletin of the Polytechnic Institute of Iași. Electrical Engineering, Power Engineering, Electronics Section
The switching of electrical equipment in normal operation conditions should be performed in optimal moments with regard to the variation of the voltage and current waveforms. Deviations from these ideal conditions will result in disruptive transient regimes, which, depending on their severity, can lead to equipment malfunctions or insulation damage. This paper continues a previous research study regarding the impact of the real switching moment regarding the known ideal conditions on various types of equipment. Previous efforts have concentrated on the study of the behavior of capacitor banks, power transformers and underground cable lines when switching is performed in different points on the voltage sine wave. This paper continues the research by studying high voltage overhead lines in the same conditions. The voltage and current waveforms are measured and analyzed for different switching times, using the EMTP software package. A comparison discussion with the previous results highlights the main findings.