Xiaofeng Liu

Dr. Xiaofeng Liu


Research Focus & Metrics

Academic Career Length

2Years (2025-Present)

(Calculated once Scilit publication data is synced: current year − year of first publication + 1)

Representative Publications

View All Publications
22 June 2025 in Buildings
Verified
Journal Article
Open access
PDF file
XLXiaofeng Liu
Xiaofeng Liu
QZQuansheng Zang
Quansheng Zang
XZXuanxuan Zi
Xuanxuan Zi
MJMingcong Ji
Mingcong Ji
CYChangyi Yu
Changyi Yu
This study analyzes the deformation and internal force changes of the main tunnel during the cutting process of the pipe jacking method for cross passages. A combination of field monitoring and numerical simulation was used to investigate a construction case of the pipe jacking method for the cross passage of Zhengzhou Metro Line 12. The study provides an in-depth analysis of the stress characteristics of the main tunnel structure during the segment-cutting process. The research findings indicate that during the pre-support stage, the internal support system helps to disperse external water and soil pressure, thereby reducing the internal forces and deformation of the tunnel. In the segment-cutting stage, the horizontal diameter of the main tunnel near the hole location gradually increases, while the vertical diameter decreases. At the same time, the stress on the bolts also rises, with the circumferential bolt stress exceeding that of the longitudinal bolts, eventually approaching their yield strength. The upper and lower ends of the tunnel opening are cut to form cantilever ends, leading to inward converging deformation. This deformation causes the internal forces to disperse toward both sides of the opening, resulting in a noticeable increase in internal force at the 90° position of the semi-cutting ring. The research findings provide a theoretical reference for understanding the deformation patterns and internal force transfer mechanisms of the main tunnel structure during the construction process of cross passages using the pipe jacking method.

20 May 2026 in Chinese Journal of Polymer Science
Verified
Journal Article
Closed access
PDF file
XLXiao-Long Li
Xiao-Long Li
XZXuan-Xuan Zi
Xuan-Xuan Zi
XLXiaofeng Liu
Xiaofeng Liu
MGMing Guo
Ming Guo
YZYan-Hui Zhong
Yan-Hui Zhong
BZBei Zhang
Bei Zhang

2 September 2026
Verified
Book Chapter
Closed access
PDF file
JFJingjie Feng
Jingjie Feng
XLXiaolong Li
Xiaolong Li
XLXiaofeng Liu
Xiaofeng Liu
PWPengfei Wang
Pengfei Wang
PLPeng Luo
Peng Luo
QZQuansheng Zang
Quansheng Zang

1 September 2025 in Journal of Physics: Conference Series
Verified
Conference Paper
Open access
QFQiang Fu
Qiang Fu
XLXiaolong Li
Xiaolong Li
XLXiaofeng Liu
Xiaofeng Liu
KHKuang He
Kuang He
JHJinhua Hu
Jinhua Hu
XYXingguo Yu
Xingguo Yu
In order to investigate the response mechanism of the main tunnel breach at the receiving end during the construction process of the pipe jacking method in the liaison channel, relying on the liaison channel project of a shield tunnelling interval of Zhengzhou Metro Line 12, the deformation, internal force and stress-strain evolution of the main tunnel structure before and after the breach are analyzed by combining the on-site strain monitoring and three-dimensional finite element simulation. The results show that: 1) the stress concentration in the half-cut ring arch waist area after the main tunnel breakthrough, the peak value of Von Mises stress reaches 13.8MPa, and the maximum value of ring strain is 413 με, and the deviation between the simulation results and the field measured data is less than 5 %. 2) The main tunnel structure shows an asymmetric deformation tendency after the breakthrough, and the pre-supporting system effectively inhibits the structural deformation in the early stage, but the breakthrough triggers the unloading of the surrounding rock and the structural stiffness change, leading to the intensification of local convergence. 3) The main tunnel structure shows a trend of asymmetric deformation after the breakthrough. The tunnel breaking construction changes the internal force distribution mode and transfer mechanism, the axial force of the cutting ring is significantly reduced, and the neighboring structures share the load through the stiffness synergistically. The results of the study can provide a theoretical basis and technical reference for the construction of pipe jacking and receiving breaching in the cross passage.