In Blitar District, exactly at Sutojayan Sub-District has become a place for flood every year because Bogel River is no longer able to relocate the flood discharge. Therefore, need to be planned a flood control construction with retaining wall begin from dimension, stability, cost estimate, and time schedule. The data required are soil testing, location map, river’s geometric section, and work unit price of Blitar District at 2019. Dimension of retaining wall is planned based on flood waters face at Q25th, the stability is calculated towards overturning, sliding and bearing capacity, axial bearing capacity of pile is calculated based on three method that is Mayerhof’s (1976), Vesic’s (1977), and Janbu’s (1976) method, while for lateral bearing capacity of pile is calculated based on Brom’s method. From the design results, the dimension of retaining wall is obtained the high 3.50 metres, upper stem’s width 0.30 metres, bottom stem’s width 0.45 metres, plate’s width 3.00 metres, heel’s width 1.55 metres, toe’s width 1.00 metres, and toe’s or heel’s high 0.35 metres. The chosen pile is pile with 20 cm × 20 cm dimension with 5 metres length for retaining wall at Sta BG. 22 and 6 metres for Sta BG. 23. With 27 pile for a 10 metres segmen, the stability against sliding and bearing capacity can be fullfiled. The reinforcement that used for plate and stem are D 16 for main tensile reinforcement, D 13 for main press reinforcement, and D 10 for divide tensile and press reinforcement. The sum of estimate cost of retaining wall is Rp. 8,626,239,000.000 with 321 work days.