Tomasz Stachoń (100)

Mr. Tomasz Stachoń (100)

Wroclaw University of Science and Technology
orcid

Research Focus & Metrics

Academic Career Length

12Years (2015-Present)

(Calculated once Scilit publication data is synced: current year − year of first publication + 1)

Representative Publications

View All Publications
11 March 2021 in Applied Sciences
Verified
Journal Article
Open access
PDF file
Jaroslaw KoniorJaroslaw Konior
Jaroslaw Konior
T(Tomasz Stachoń (100)
Tomasz Stachoń (100)
The purpose of the research presented in the article is to identify the impact of the processes associated with the broadly understood maintenance of old residential buildings with a traditional construction on the size and intensity of the wear of their elements. The goal was achieved by analyzing the symptoms of the technical wear process, which involved the understanding of the mechanism of the occurrence of the phenomenon of damage, and the identification of the size and intensity of the damage to the elements of the evaluated buildings. The consequence of systematizing the most important processes that influence the loss of functional properties of residential buildings was the creation of the authors’ own qualitative model and its transformation into a quantitative model. This, in turn, enabled a multi-criteria quantitative analysis of the cause and effect phenomena—“damage-technical wear”—of the most important elements of downtown tenement buildings to be carried out in fuzzy conditions, i.e., uncertainty concerning the occurrence of damage and the wear process. The following key question was answered in the subjective expert assessment of the technical condition of an evaluated residential building: what is the probability of the wear of an element, which may be more or less correlated with its average maintenance conditions, or more simply, what is the probability that the element is more or less (approximately) worn? It has been proven that the conditional probability of the technical wear of an element in relation to its damage increases with the deterioration of the maintenance conditions of the building, and this increase is very regular, even in the case of different building elements. This probability is characterized by a low standard deviation and a narrow range of the dispersion of results in the case of various elements with regards to each of the considered building maintenance conditions.

27 June 2024 in Applied Sciences
Verified
Journal Article
Open access
PDF file
Mariusz SzóstakMariusz Szóstak
Mariusz Szóstak
T(Tomasz Stachoń (100)
Tomasz Stachoń (100)
Jaroslaw KoniorJaroslaw Konior
Jaroslaw Konior
Forecasting the actual cost of the implementation of a construction project is of great importance in the case of technical management and enables financial resources to be initially maintained in a controlled manner and in a way that is as close as possible to the actual state. Based on the analysis of the developed knowledge base, which contains data from 612 reports of the Bank Investment Supervision regarding 45 construction projects from 2006 to 2023 with a total value of over PLN 1,300,000,000, best-fit curves were determined, and the expected area of the cumulative actual cost of selected construction projects was specified. The obtained polynomial functions and graphs of real areas of cost curves (in the form of nomograms) constitute a reliable graphical representation that enables the application of research results in typologically similar groups/sectors of the construction industry. The elaborated course of the cumulative cost curve (CCCC) as a method of CAPEX prediction in selected construction projects stands for a combined approach of the S-curve, polynomial functions, and the best-fit area of cumulative earned cost. The research used scientific tools that can be practically and easily used by both managers and participants of the investment process.

17 April 2025 in Applied Sciences
Verified
Journal Article
Open access
PDF file
T(Tomasz Stachoń (100)
Tomasz Stachoń (100)
Mariusz SzóstakMariusz Szóstak
Mariusz Szóstak
Jaroslaw KoniorJaroslaw Konior
Jaroslaw Konior
The article presents research findings on updating financial contingency estimates for typologically diverse construction projects. The research was carried out from 2006 to 2024 on a sample of 41 investment tasks, represented by five different construction sectors, in which 547 measurements were made of the deviation of the earned cost of construction works from its planned values. The study found significant variability in the cost performance index (CPI) across different construction types. Box plots were determined, and their statistical interpretation made it possible to determine the actual financial contingency, the variation in which in the groups of residential, office and hotel buildings, as well as shopping and logistics centres, is in the range of 3% to 30%. The article concludes with recommendations for banks financing investment tasks in the direction of making financial contingency more realistic when making sustainable lending decisions.

29 April 2024 in Przegląd Budowlany
Verified
Journal Article
Closed access
Jaroslaw KoniorJaroslaw Konior
Jaroslaw Konior
T(Tomasz Stachoń (100)
Tomasz Stachoń (100)
W artykule przedstawiono analizę i ocenę planowanego,aktualnego i rzeczywiście wypracowanego kosztu różnychprzedsięwzięć budowlanych objętych próbą badawczą o liczebnościponad pół tysiąca pomiarów. Zastosowanie metodyki EVM pozwoliłona ocenę w zakresie porównania planowanego, poniesionegoi rzeczywiście wypracowanego harmonogramu i kosztu orazwskazanie podstawowych przyczyn odchyleń kosztowych od wartościwypracowanych. Zaobserwowano analogie w ułożeniu krzywychskumulowanych przepływów pieniężnych, zarówno w ramachtych samych grup obiektów budowlanych, jak i pomiędzy nimi.

27 February 2024 in Przegląd Budowlany
Verified
Journal Article
Closed access
Jaroslaw KoniorJaroslaw Konior
Jaroslaw Konior
T(Tomasz Stachoń (100)
Tomasz Stachoń (100)
Celem artykułu jest analiza i ocena przebiegu zróżnicowanychprzedsięwzięć budowlanych w zakresie wypracowanegokosztu oraz wskazanie podstawowych przyczyn odchyleńkosztowych robót rzeczywiście wykonanych na budowie. Z uwagina utylizację około 75% środków finansowych w fazie wykonawczejdla etapu realizacji robót dokonano analizy zgodnie z metodykąEarned Value Method pozwalającą na ocenę rzeczywiścieosiągniętych budżetów różnorodnych zadań inwestycyjnych. Zaobserwowanoanalogie w ułożeniu krzywych skumulowanychprzepływów pieniężnych, zarówno w ramach tych samych grupobiektów budowlanych, jak i pomiędzy nimi