This paper presents a case study on the rehabilitation of a fire-damaged structure and describes the results of a site investigation and tests, leading to a plan for the rehabilitation of the structure. The fire took place in the main control room of a thermal power plant and lasted about three hours until it was finally extinguished. To set up a rehabilitation plan for the damaged structure, a visual inspection of the damaged condition was first carried out, which was followed by analysis and on-site material tests indicating the degree of neutralization progress in the remaining structure. Specimens of damaged concrete and reinforcing bars were sampled and tested for their residual strengths. As a conclusion, two methods of rehabilitation were suggested considering the current condition of the structure and the sequence of construction.
30 April 2012 in Journal of the Korea Concrete Institute
Reshoring makes a floor support its own weight and decreases the construction load in the lower levels. However, a significant concern regarding reshoring lies in its safety and serviceability when shores are replaced while the construction load of the upper levels is applied. To investigate this concern and compare the construction load in shores and reshores, reinforced concrete (RC) beam-column joints at early ages were tested in the laboratory and were also monitored at a construction site. The specimens at ages of 2 and 3 days showed a shear-compression failure, and the specimens at ages of 7 or more days showed sufficient flexural behaviors. The test also found that the beam-column joints have sufficient stiffness even at the earliest ages that the joint can be safely assumed to be fully restrained regardless of the concrete age. Analysis of the test results showed that reshoring at 5 days of concrete age is 55% safer than keeping the shores until the age of 28 days, and no serviceability pr...