This study investigates the surrounding rock failure caused by the fracture line of the main roof above the gob-side roadway during fully mechanized top-coal caving mining in a 19 m thick coal seam. As mining progresses, stress concentration occurs in the roadway roof. Furthermore, the fracture line of the main roof above the roadway poses a significant threat to the structural stability of the gob-side roadway, leading to the localized failure of the roof structure, which consequently affects the safe and efficient production of the mine. This study investigates the shear failure mechanism of the roadway top coal and analyzes the failure characteristics and stress evolution law of the surrounding rock when the main roof fracture line (MRFL) is located above the roadway through three integrated approaches: theoretical analysis, numerical simulation, and physical similarity modeling. To effectively mitigate damage to the top coal, it is proposed to implement a five-hole tray coupled with high-strength prestressed anchor cables for reinforcing the surrounding rock, while compact wooden piles in combination with single pillars are employed to strengthen the roadway support control measures. It is verified by field tests that these control methods significantly improve the stability of coal above the entry and greatly mitigate the likelihood of surrounding rock failure.
The fault fracture zone has the characteristics of low strength and poor water resistance. These factors often lead to stress concentration and significant deformation during roadway excavation. In order to improve the anti-deformation ability and strength of the surrounding rock and reduce the support pressure, taking the roadway passing through the F2 fault in the Wugou coal mine as an example, the evolution characteristics of the surrounding rock of the roadway passing through the fault were studied using FLAC3D numerical simulation software, and the stress evolution law and failure characteristics of the surrounding rock in three stages of the roadway driving through the fault fracture zone were analyzed. The slurry diffusion characteristics under different grouting hole layouts were studied using COMSOL software, and the effectiveness of ground directional grouting (combined directional drilling technology with ground grouting technology) reinforcement technology was explored via similar simulation experiments. After the pre-grouting reinforcement of the surrounding rock by the ground directional hole in the field, the fault fracture zone was successfully excavated. The key technical system of the shield roadway passing through the fault based on the directional drilling and ground grouting technology was summarized and put forward. The three-hole drilling and the circumferential four-hole drilling layouts were used to realize the grouting in the fault fracture zone. Engineering practice shows that ground directional grouting has significant advantages and improves the mechanical properties of the broken weak surrounding rock. The deformation of the roadway roof is 128 mm, and the deformation of the two sides is controlled within 100 mm. This method greatly improves the stability of the roadway and has been verified by the field results.